  • To conduct model studies and propose the solutions for Flood Protection Works, Spillways, Weirs, River Bridges and Hydraulic Structures of Canals / Drains.
  • To optimize design of Hydropower Projects.
  • To optimize design of Barrages, Dams and Reservoirs.

LAYOUT PLAN OF EXISTING NANDIPUR RESEARCH STATION

                 LAYOUT PLAN OF EXISTING NANDIPUR RESEARCH STATION

MAJOR ACHIEVMENTS OF HYDRAULICS WING

  • Kotri Barrage & U/S training works (1948)
  • Taunsa Barrage & U/S training works (1952)
  • Guddu Barrage & U/S training works (1956)
  • Flood control studies on Ravi &  Chenab rivers
  • River diversion & Spillway study of Warsak dam
  • Indus Basin Replacement works involving construction of five Barrages (Chashma, Taunsa, Rasul, Marala, Trimmue) & eight link canals (1960)
  • Model studies of Mangla Dam
  • Model studies of Tarbela Dam
  • Model studies for Detail Design of Kalabagh Dam (1984)
  • Model studies of Bhasha Diamer Dam (2008).
  • Model studies of Ghazi Brotha Hydropower Project.
  • Model studies conducted for Iran, Yemen & Libya.
  • Model studies of the projects under Flood Protection Sector Project – II (FPSP-II) of the country.

SPECIAL  ACHIEVEMENTS OF HYDRAULICS WING

  • Models of tunnel No. 3, 4 & 5 of Tarbela Dam  tested at an International Laboratory.
    • Failed at Site during first operation.
    • Re-tested at Nandipur, performing satisfactorily uptill now.
  • Tarbela spillways  with flip bucket  tested at an International Laboratory.
    • Failed at site.
    • Re-tested at  Nandipur and performing properly.
  • Spillway of Nandipur Hydel Power Station designed, Model tested and executed by Czechoslovakia.
    • Failed when Operated at 1/3rd of design discharge.
    • Nandipur devised a practicable design. Now performing successfully.
  • Chashma Hydel Power Project Studies
    • Nandipur Cost   =  Rs. 1 Million
    • Sogria – France Cost  =  Rs. 15 Million
    • Recommendations were same.

PROJECTS UNDER STUDY

  • Model study of Chianwali Hydropower Project on UCC.
  • Model study of Deg Outfall Hydropower Project.
  • Model Study For Construction Of Bridge Over Sutlej River To Link Chishtian With Burewala
  • Model Study For Construction Of Bridge Over Chenab River Near Bhowana
  • Model Study of Bridge Connecting Layyah to Taunsa over Indus River.
  • Model Study of training works for Shoyke River.
  • Model study for construction of new Barrage on Swat River.
  • Sectional model of Main weir of new Barrage over Swat River.
  • Sectional model of Undersluice of new Barrage over Swat River.
  • Model Study of Chenab River for New Khanki Barrage.
  • Comprehensive model study of Trimmu Barrage.
  • Model Study of Indus River D/S Sukkar Barrage to Larkana Khairpur Bridge (Upper Reach).
  • Model Study of Indus River D/S Sukkar Barrage to Larkana Khairpur Bridge (Lower Reach).
  • Model Study of River Indus for Protection Canal Link-1 D.G. Khan Zone.
  • Model Study of Ring Road for Realignment of Northern and Southern loops along Ravi River.
  • Model Study of Flooding Problem U/S of Kabul River and Jindi Nullah Bridges on M-1 in Peshawar.
STUDIES CONDUCTED BY HYDRAULICS WING DURING THE LAST 5 - YEAR
  • Model Studies for River Training Works    =  60
  • Model Studies for Optimization of Bridges over Rivers    =    8
  • Model Studies for Rehabilitation of Punjab Barrages  =  10
  • Model Studies of Dams and its Pertinent Structures and Hydropower Projects  =  22
  • Model Studies for Canal Head Regulators at Barrages  =    3
  • Hydrographic Survey of Dams in Punjab   =    4
  • Total  =   107